Completed project: Reconstruction and rehabilitation of the street network in the village of Ravadinovo, Sozopol municipality
Construction company "Biad-S" EOOD successfully completed the implementation of the object "Reconstruction and rehabilitation of the street network in the village of Ravadinovo, Sozopol municipality", implemented within the agreed deadline and in accordance with all technical, investment and regulatory requirements.
The project includes a complete renovation of sections of the street infrastructure with a total length of 618.75 linear meters, with the main focus being placed on increasing the bearing capacity of the pavements, improving operating conditions and ensuring a safer and more sustainable transport environment for residents and visitors to the settlement.
Main parameters of the object:
-
Object: Reconstruction and rehabilitation of the street network
-
Location: Ravadinovo village, Sozopol municipality
-
Value: 978,659.51 BGN excluding VAT
-
Total length of streets: 618.75 m
-
Deadline: 100 calendar days
-
Commissioned: 13.10.2025
During the implementation of the project, all planned construction activities were implemented, covering the delivery and use of materials, use of the necessary mechanization and equipment, organization and coordination of construction processes, as well as the implementation of accompanying works related to logistics, warehousing and preparation of the construction site.
Particular attention was paid to compliance with the requirements for health and safety at work, quality control through the performance of the necessary tests and inspections, as well as the proper management and removal of construction waste to the designated locations. All activities were completed in full, according to the approved projects and contractual commitments.
With the commissioning of the site, the street infrastructure in the village of Ravadinovo has been significantly improved, with the implemented project contributing to better functionality, sustainability and long-term operation of the constructed facilities.
With this completed object "Biad-S" EOOD continues to strengthen its experience and reliability in the implementation of infrastructure projects on the territory of the municipality of Sozopol and the region.