Human Resources Development Program SEE HERE

RHI – Smolyan

Energy renovation of the RHI building – Smolyan

Engineering · Design · Construction · Author's supervision | 2025 – 2026

"BIAD-S" EOOD is implementing the complete renovation of the administrative building of the Regional Health Inspectorate - Smolyan within the framework of a project to implement energy efficiency measures and ensure an accessible environment.

The building was built in 1962, on four floors, with a monolithic reinforced concrete structure and a built-up area of 1,631.75 sq m.

The object is running in the mode of full engineering, including preparation of a technical project for all necessary parts, execution of construction and installation works and exercise of author's supervision.

Within the framework of the renovation, basic measures were implemented to improve the energy performance, technical condition and functionality of the building. The joinery was replaced and the roof was insulated. The heating system was modernized by switching from industrial gas oil to natural gas, and to reduce the consumption of electricity from the network, a photovoltaic installation for own consumption.

A new electrical installation and new lighting have been installed, a fire alarm system has been installed, and the lightning protection system has been replaced. The approach to the building has been redesigned in accordance with the requirements for ensuring an accessible environment.

The implementation of the project improves the energy efficiency, safety and operational characteristics of the building, as well as the working conditions and service for visitors of the RHI - Smolyan.

Object: "Engineering - preparation of a technical project, performance of construction and installation works and exercise of author's supervision of a site: "Implementation of energy efficiency measures and ensuring accessibility in the building of the Regional Health Inspectorate - Smolyan"

Value: 773 354,54 euros excluding VAT

Total area: 1631.75 sq.m.

Deadline: 400 days